2. About the Company

[GRI 2-1 • 2-2 • 2-6]

2.1 Overview

Full company name - Public Joint Stock Company "Second Generating Company of the Wholesale Electricity Market", short company name - OGK-2, PJSC (hereinafter also referred to as OGK-2, the Company, the Society). Gazprom Energoholding LLC (100% subsidiary of Gazprom PJSC) is the controlling shareholder of OGK-2. Our Company was established on March 9, 2005. Further, in the course of the reform of the Russian electric power industry, by the end of 2009 Gazprom Energoholding LLC consolidated the controlling stake in the Company.

OGK-2, PJSC is the largest Russian thermal generation company with an installed electric capacity of 16.3 GW and an annual revenue of about 143 billion rubles.
The company is registered: 356128, Russian Federation, Stavropol Territory, Izobilnensky District, Solnechnodolsk village

In fact, the majority of the Company's employees (excluding branches and subsidiaries) work in St. Petersburg: 196605, St. Petersburg, 66 Peterburgskoye chaussée, bldg 1, lit. A.

The principal operations of OGK-2, PJSC are production and sales of electric (capacity) and thermal power. The main sales market is the wholesale electric power (capacity) market. As part of this activity, OGK-2 ensures operation of power equipment in accordance with applicable regulations, conducts timely and high-quality repairs, technical re-equipment and reconstruction of power facilities.

2.1.1 Investment attractiveness

Capitalization as of December 31, 2022 is 60.8 billion rubles *

* Source: https://www.moex.com/a8313

Dividends: retrospective / debt burden

2.1.2 Corporate structure

[GRI 2-2]

2.1.3 Our principles and valuables

[GRI 2-23]

In its sustainable development activities, the Company adheres to the following principles: 

The Company 's corporate values are: 

 

We are constantly improving our approaches and developing, following the best Russian and international practices.

2.2 Our history and highlights of the year

2.2.1 History

2005 Open Joint Stock Company Second Generating Company of the Wholesale Electricity Market (OGK-2, OJSC) was registered in Izobilny town (Stavropol Territory) in March 2005.
2006 In September 2006, the power station plants ceased their activities as legal entities and became part of OGK-2, OJSC as branches.
2007 In October 2007, the placement of additional shares of OGK-2, OJSC among an unlimited number of investors (IPO) was completed.
2008 In July 2008, the Company was reorganized through the merge of OGK-2 Holding and OGK-2, OJSC (the final stage of the reorganization of UES of Russia JSC). As a result of the reorganization, the shareholders of RAO UES of Russia became the shareholders of OGK-2, OJSC.
2011 In June 2011, the Annual General Meetings of Shareholders of OGK-2, OJSC and OGK-6, OJSC took place, where it was decided to reorganize the Companies by merging OGK-6 with OGK-2.
In November 2011, as a result of the reorganization, the largest Russian thermal generating company OGK-2, OJSC was founded with 11 branches.
2013 In January 2013, a new station of the Company, the Adler TPP, was put into operation, the most modern power generation facility in Sochi.
2018 December 2018 – June 2019: Commissioning of two new power units at Grozniy TPP.
2019 In February 2019, the Board of Directors of OGK-2, PJSC decided to establish a branch of OGK-2, PJSC – Svobodnensk TPP.
In September, obsolete heat-generating equipment at Serov SDPP was decommissioned.
2020 In January 2020, OGK-2, PJSC and Yenisei TGC, JSC, a subsidiary of Siberian Generating Company (part of the SUEK group), entered into an agreement on the sale of Krasnoyarsk SDPP-2. The total transaction value was 10 billion rubles (excluding VAT). It included movable and immovable property of the Krasnoyarsk SDPP-2, coal reserves, spare parts, other material stock and technical resources.

2.2.2 Major Events of the Year

February
OGK-2 received certificates of conformity for its Quality Governance System.
May
At Novocherkassk SDPP, the overhaul of the power unit has been completed.
June
50% of net profit under RAS are dividend payments for 2021. The Company allocated 10,663 million rubles for the payment of dividends. (0.0965536029864 rubles per ordinary share).
August
At Novocherkassk SDPP, the overhaul of a power unit has been completed.
October
The required capacity of CSA No.4 (CCGT-180) facility of the branch of OGK-2, PJSC - Adler TPP, was provided.
OGK-2 employees won two prizes at the 11th Competition for young specialists and innovators from Gazprom Energoholding LLC.
November
Decommissioning Acts for TG-1, TG-3 (170 MW) of Troitsk SDPP, a branch of OGK-2, were signed.
November
Rating agency AK&M included OGK-2, PJSC in the rating of companies with the highest level of information transparency concerning reported sustainable development (top 17 companies, scoring 80.6 points).
December
The required capacity of CSA No.5 (CCGT-180) facility of the branch of OGK-2, PJSC - Adler TPP, was provided.
December
Kirish SDPP became the winner of the ‘Business, Developing Region’ contest late 2022 among large businesses in ’Digital Transformation of Business’ nomination.

2.2.3 Ratings and awards

2.3 Key results in 2022

[GRI 2-6]

2.4 Business model *, **

* The number of personnel is indicated taking into account external part-time workers.
** Financial results are based upon RAS data.

2.5 Geographical reach **

[GRI 2-6]

* Operated by OGK-2